The Petroleum Industry Act 2021 (the PIA) introduces a more structured framework for the relinquishment of petroleum acreages, moving beyond the limited guidance of its predecessor, the Petroleum Act 1969.

Under the PIA and regulations issued by the Nigeria Upstream Petroleum Regulatory Commission (NUPRC), clear provisions now govern the circumstances in which licensees and lessees are required to relinquish portions of their acreages in the case of mandatory relinquishment or circumstances permitting them to do so in the case of voluntary relinquishment. This shift positions relinquishment as a strategic regulatory tool for reducing idle assets and efficient resource development.

As Nigeria intensifies efforts to boost crude oil production, the effective implementation of this framework has the potential to unlock underutilised assets and attract new investment into the upstream sector.

In this Newsletter, we explore the legal framework governing relinquishment under the PIA and NUPRC’s regulations and examine the implications for operators and investors navigating Nigeria’s evolving oil and gas industry.

What acreage relinquishment means

The PIA does not define relinquishment. In industry usage, however, it describes a licensee or lessee returning part or all of its allocated acreage to the government after a set period and under set conditions.

The purpose is practical. Relinquishment pushes holders to explore and develop their acreage. Otherwise, undeveloped portions, including subsurface depths, revert to the Federal Government, which can then offer them to new investors through competitive bid rounds.

The change from the old regime is significant. Under the Petroleum Act 1969, only oil mining lease holders had to relinquish, and only half the leased area ten years after grant. The detail was largely left to the Minister’s discretion.

Mandatory acreage relinquishment

The PIA, the Significant Crude Oil and Gas Discovery Regulations 2023 and the Acreage Management Regulations 2024 set out several triggers.

  • Declaration of no interest. After an exploration discovery, a licensee has 180 days to say whether it will appraise. Appraisal may run for up to three years. Where the licensee declares no interest, the NUPRC may direct it to relinquish the relevant parcels.
  • Failure to declare a significant discovery. Where the NUPRC concludes a declaration should have been made, it may issue a Non-Declaration Notice giving 30 days to respond. Silence is treated as a declaration of no interest. A late declaration made before the NUPRC orders relinquishment avoids it, but attracts a penalty of $10,000 for each day of default.
  • No commercial discovery after retention. A retention period may last up to ten years. If no commercial discovery is declared by the end, the retention area is relinquished automatically and the licence over it expires.
  • No field development plan. After declaring a commercial discovery, a licensee has two years to submit a field development plan with a work commitment. Missing that deadline triggers automatic relinquishment.
  • Expiry of a prospecting licence. On expiry, the licensee must give up every area that is not an appraisal, retention, lease or commercial discovery area. Thirty days before expiry, it must submit a map of the areas it intends to keep.
  • Ten years into a mining lease. Under section 88(5), a lessee must relinquish parcels outside the boundary of a producing field. It must also give up formations deeper than the deepest producing formation.

The mining lease process has firm timelines. Within 90 days before the tenth anniversary, the lessee submits boundary and contour maps. The NUPRC then has 60 days to decide what must go. A dissatisfied lessee may object within 15 days, and the NUPRC issues a final decision within 60 days. In practice, therefore, the Commission acts as final arbiter, since courts review such administrative decisions only on narrow grounds.

Voluntary relinquishment and surrender

A holder may also choose to relinquish. However, the NUPRC will only approve where the holder has met its licence obligations, including environmental ones, and paid outstanding rents and statutory payments. The Commission must also approve the shape and size of the area.

Separately, section 89 of the PIA allows a licensee or lessee to surrender part or all of its area. It must have met its obligations and give the Commission three months’ written notice.

Why it matters for operators

As Nigeria pushes to raise crude oil production, relinquishment has become a live strategic issue. Holders should track every deadline, keep declarations current and plan field development early. Our note on new commercial regulations in Nigeria’s upstream petroleum sector and our Oil and Gas 2025 Wrap-Up and 2026 Outlook cover related developments.